Many engineering choices depend upon economics. You must select the path forward that will earn the most (or lose the least). The three most common methods for evaluating economic value of projects are simple payback, net present value (NPV) and internal rate of return (IRR). Each offers a different type of answer. Simple payback details a duration. NPV gives a total value. IRR yields a percent or fraction. All three have specific situations where they might be the right approach.
[pullquote]
Let’s focus here on when to use NPV versus IRR. Both use a time-discount factor. It recognizes that money in-hand today is worth more than money in the future. Both NPV and IRR consider cost of funds (COF), which is an externally imposed cost of using capital.
Capital can come from different sources. If the funds are from a loan, COF includes the interest rate on the loan plus the loan’s administrative and overhead costs. If the money is from equity, COF represents the return required to tempt investors to buy shares in a firm.
NPV is defined as the expected total value of a project above the cost of funds required to finance the project. The simplest definition of IRR is that it is the cost of funds that brings the NPV down to zero.
Table 1 illustrates simplified examples of three projects. All three use a basis that all funds are expended or received at the start of the year. Table 1 includes the year, cash flow, COF, discounted cash flow (DCF) and total NPV.
• Project 1 has a high NPV and a low IRR.
• Project 2 has a low NPV and high IRR.
• Project 3 is shown with only an NPV.
This looks confusing? Which would be the better project to invest in?
NPV concentrates on total wealth creation. A higher NPV gives a higher total wealth gain. In general, use NPV when:
• The projects are exclusive. You can do either Project 1 or Project 2 but not both.
• The projects have complex cash flow patterns. Project 3 is a good example.
• The projects have different expected productive lives. Again, Project 3 is a good example.
• The projects have variable expected COF values, as in Project 3.
IRR concentrates on investment efficiency. In general, use IRR when:
• The projects are additive. You can invest in both Project 1 and Project 2 if you want.
• The projects have smooth cost flow patterns.
NPV tends to be more flexible. NPV can handle nearly any combination of project life, cash flow quantity and direction, and allows for variable COF over time. NPV nearly always is the right choice when projects are exclusive. An example is building a plant in Location A (Project 1) versus Location B (Project 2) to supply a fixed market. You only will build one plant. Once a choice is made, the other option is eliminated. Many other cases exist, including situations with limited supply of feed or physical space constraints inside an existing plant. NPV investment decisions tend to favor large projects over smaller ones because large cash flows can give larger NPV totals.
IRR tends to be simpler to understand. Many people prefer to think in percentages rather than in quantities. The examples in Table 1 use numerical methods to get the NPV and IRR values. IRR assumes you have a free choice of projects. A nearly perfect example of using an IRR calculation is investment in the stock market. You can invest in many stocks. Investing in one stock does not shut off the option of investing in additional stocks as well. IRR investment decisions tend to favor smaller projects that have relatively high returns.