Shutterstock 653034436 636acff32c478 63e711181118d

Energy Saver: Why Continue To Do That?

Jan. 21, 2019
Many unnecessary entrenched procedures afflict plants

My jaw dropped and I broke into a cold sweat as I stared in shock and disbelief. When I finally regained the power of speech, I stammered to the young process engineer beside me, “Why do you do THAT!”

She looked a little startled, but then shrugged her shoulders and said, “That’s the way we have always done it. It was built that way.”

Reviewing process flow diagrams (PFDs) isn’t usually such an exciting exercise, but this was an exception. The drawing showed a distillation column — one of the largest in a very big chemical complex — with a steam reboiler. It was impressive, but not particularly unusual. What astonished me was the fin fan cooler on the feed stream. Why on earth…

Distillation is a separation process that uses heat to drive successive stages of vaporization, mixing and condensation. The heat for this process comes from the reboiler. However, if the feed entering the column is subcooled, which was true in this case, the reboiler must provide additional heat to raise the feed to its bubble point before it can start vaporizing. Cooling the feed stream ahead of the column increases the load to the reboiler. In the vast majority of cases, this is a bad idea; it increases energy costs. The exceptions are generally where the cost of condensing the overheads dominates, as in some low-temperature distillation systems; however, that didn’t apply in this case.

After that mind-numbing lightbulb moment, I had several intense conversations with operations managers and technical specialists on the site, while the young process engineer ran multiple simulations of the column. After several weeks, we were able to persuade the plant manager to turn off the fan on the cooler. Steam demand for the reboiler promptly dropped by more than 30%, saving the plant $1,000,000/year, without any investment.

Even with the fan off, natural convection in the fin fan cooler still caused significant heat loss. We proposed a small project to eliminate that loss by installing a bypass around the cooler. This would save an additional $200,000/year with a very good payback. However, due to other priorities, the project wasn’t implemented.

I have presented this example many times [1], and a number of people have proposed reasons why the designers included the feed cooler. A leading possibility is that they anticipated higher feed temperatures that would cause additional vapor traffic in the rectifying section of the column and overload the overhead condenser. If so, adding the feed cooler at the design stage would avoid installing a larger overhead condenser, and perhaps also increasing the diameter of the rectifying section — but at the cost of significantly higher energy consumption.

My best guess is that the designers expected occasional upset conditions that would require removing heat from feed, and the feed cooler was intended only for occasional use to handle these situations. However, after the plant was commissioned, it became standard practice to run the fans continually. After all, the equipment was there; why not run it? So, it ran, wasting energy for more than a decade, until we happened upon it in a PFD review.

Operating practices tend to become entrenched over time. Operators may dutifully follow procedures that were developed when their plant was commissioned, even when throughput, feed stocks, product slates, and a host of other factors have changed. Also, they sometimes make changes as a result of short-term problems. For example, running the feed cooler to deal with an abnormally high feed temperature, or bypassing pumparound coolers during cold weather and forgetting to revert when conditions change. As a result, many valves are closed when they should be open, or open when they should be closed; many pieces of equipment are in use when they should be off or vice versa; and many process set points are chosen without proper consideration of their impact on energy utilization. I have encountered lots of these situations over the years, and perhaps you have, too. If you’d like to share some examples, I’d be happy to hear from you.

REFERENCE

1. Rossiter, A. P., “Back to the Basics,” Hydrocarbon Engineering, Vol. 12, No. 9, pp. 69–73 (September 2007).

About the Author

Alan Rossiter | Energy Columnist

Alan Rossiter is a former contributor for Chemical Processing's Energy Saver column. He has more than 35 years of experience in process engineering and management, including eight years in plant technical support, design and research with Imperial Chemical Industries (ICI, United Kingdom) and nine years in energy efficiency and waste minimization consulting with Linnhoff March, before starting his own business. In 2019 he joined the University of Houston as Executive Director, External Relations for UH Energy. He is a chartered engineer (U.K.) and a registered professional engineer in the state of Texas. His latest book, Energy Management and Efficiency for the Process Industries, coauthored with Beth Jones, was published by John Wiley & Sons in 2015. He is a Fellow of the American Institute of Chemical Engineers and a Past Chair of the South Texas Section of the AIChE. 

Sponsored Recommendations

Keys to Improving Safety in Chemical Processes (PDF)

Many facilities handle dangerous processes and products on a daily basis. Keeping everything under control demands well-trained people working with the best equipment.

Get Hands-On Training in Emerson's Interactive Plant Environment

Enhance the training experience and increase retention by training hands-on in Emerson's Interactive Plant Environment. Build skills here so you have them where and when it matters...

Rosemount™ 625IR Fixed Gas Detector (Video)

See how Rosemount™ 625IR Fixed Gas Detector helps keep workers safe with ultra-fast response times to detect hydrocarbon gases before they can create dangerous situations.

Micro Motion 4700 Coriolis Configurable Inputs and Outputs Transmitter

The Micro Motion 4700 Coriolis Transmitter offers a compact C1D1 (Zone 1) housing. Bluetooth and Smart Meter Verification are available.