HOW BEST DO WE SUPPLY AIR TO NEW PUMPS?
Figure 1. Compressed air system services a variety of loads at refinery adding air diaphragm pumps.
DO AN ANALYSISThis is a complicated problem without knowing more about the air demand in the different units of the refinery. The best approach is to do a survey of usage rates by each unit. This could be difficult and time-consuming if meters aren't in place. If not, consider installing orifice plates at each unit. The idea is that 300 scfm is a lot of air. Using an estimate of about $250/year/scfm, this is an additional cost of about $75,000/year; so the demurrage costs will have to be substantial. By doing a load capacity study at normal flow and at peak demand, it will be possible to determine how far you need to go back to the main header. This affects the overall viability of the project.
Another approach to this survey is to count the number of control valves and automatic valves in service. A crude estimate of demand is 1 scfm/valve. This assumes that compressed air isn't used for other applications — for such applications, it might be possible to get the maximum design rates from vendors. Of course, time of service can only be estimated roughly.
There's another way to look at this problem: Consider an analysis of equivalent length (see Figure 2). It clearly shows that in most cases a 2-in. pipe is sufficient for 300 scfm, assuming the run length to the tie point is less than a mile. Based on this analysis, I would tie into the 3-in. blind flange located on the FCC header.
One simple solution might be to link across one of the 2-in. lines allowing the burden to be shared. This is a common solution where intermittent demands can be larger than a single draw alone.
Once the loads are established, it will be necessary to confirm if the 3-in. tie-point offers the least disruption of the pressure available.
Dirk Willard, lead process engineer
Fluor Global Services, Inver Grove Heights, Minn.